1. A ________________ is a temporary endeavor undertaken to create a unique product, service, or
result.
a) Program
b) Process
c) Project
d) Portfolio
Ans: C Project
2. Which of the following is not a potential advantage of using good project management?
a) Shorter development times
b) Higher worker morale
c) Lower cost of capital
d) Higher profit margins
Ans: C. Lower Cost of Capital
3. Which of the following is not an attribute of a project?
a) Projects are unique
b) Projects are developed using progressive elaboration
c) Projects have a primary customer or sponsor
d) Projects involve little uncertainty
Ans: D. Project involve little uncertainty
4. Which of the following is not part of the triple constraint of project management?
a) Meeting scope goals
b) Meeting time goals
c) Meeting communications goals
d) Meeting cost goals
Ans: C. Meeting Communication Goals
5. The first stage of any project is
a) Proposal
b) Conceptualization
c) Implementation
d) Management
Ans: B. Conceptualization
6. __________________ is the application of knowledge, skills, tools and techniques to project
activities to meet project requirements.
a) Project management
b) Program management
c) Project portfolio management
d) Requirements management
Ans: A. Project Management
7. Project portfolio management addresses ____________________ goals of an organization, whileproject management addresses _________________ goals.
a) Strategic, tactical
b) Tactical, strategic
c) Internal, external
d) External, internal
Ans: A. Strategic, Tactical
8. Several application development projects done for the same functional group might best be
managed as part of a
a) Portfolio
b) Program
c) Investment
d) Collaborative
Ans: B. Program
9. Which of the following is not one of the top ten skills or competencies of an effective project
manager?
a) People skills
b) Leadership
c) Integrity
d) Technical skills
Ans: D. Technical Skills
10. What is the certification program called that the Project Management Institute provides?
a) Microsoft Certified Project Manager (MCPM)
b) Project Manager Professional (PMP)
c) Project Management Expert (PME)
d) Project Management Mentor (PMM)
Ans: B. Project manager professional (PMP)
11. A _________________ is a series of actions directed towards a particular result.
a) Goal
b) Process
c) Plan
d) Project
Ans: B. Process
12. ____________________ Processes include coordinating people and other resource to carry out the project plans and produce the products, service, or results of the project or phase.
a) Initiating
b) Planning
c) Executing
d) Monitoring & controlling
Ans: C. Executing
13. Which process group normally requires the most resources and time?
a) Initiating
b) Planning
c) Executing
d) Monitoring and controlling
Ans: C. Executing
14. A work breakdown structure, project schedule, and cost estimates are outputs of the process.
a) Initiating
b) Planning
c) Executing
d) Monitoring and controlling
Ans: B. Planning
15. Which process group includes activities from each of the nine knowledge areas?
a) Initiating
b) Planning
c) Executing
d) Monitoring and controlling
Ans: D. Monitoring and Controlling
16. Project management as a profession is almost unique in having institutions concerned with its development who promote what they term their
a) Body of language
b) Body of knowledge
c) Strategy
d) Work
Ans: B. Body of knowledge
17. Initiating involves developing a project charter and preliminary project scope statement, which are part of the project _____________________ management knowledge.
a) Integration
b) Scope
c) Communications
d) Risk
Ans: A. Integration
18. A ________________ describes how things should be done, and different organizations often have different ways of doing things.
a) Regulation
b) Process
c) Standard
d) Methodology
Ans: D. Methodology
19. ___________________ involves measuring progress toward project objectives and talking
corrective actions.
a) Initiating
b) Planning
c) Executing
d) Monitoring and controlling
Ans: D. Monitoring and controlling
20. What type of report do project teams create to reflect on what went right with the project?
a) Lessons – learned report
b) Status report
c) Final project report
d) Business case
Ans: A. Lessons-learned report
21. Project manager is responsible for
a) Overseeing change
b) Cross functional activities
c) Ever changing set of tasks
d) All above
Ans: D. All above
22. Many people use ________________ to have a standard format for preparing various project management documents.
a) Methodologies
b) Templates
c) Project management software
d) Standards
Ans: B. Templates