What do you understand by “Centralised Production Planning and Control”?

 

 

Note: Solve any 8 Questions

 

 

  1. To compare three sites, the various factors are listed, as given below. Select the optimal location and give reasons for your choice:

 

 

Site A

Rs.

Site B

Rs.

Site C

Rs.

Rent

20,000

10,000

10,000

Labour

1,35,000

1,30,000

1,60,000

Freight Charges

81,000

64,000

28,000

Taxes

Nil

3,500

2,000

Power

6,000

6,000

6,000

Community attitude

Indifferent

Want business

Indifferent

Employee Housing

Excellent

Adequate

Poor

 

 

  1. What are the principal considerations for location of:

i.                    Steel industry around Bihar

ii.                  Zinc smelter Plant at Udaipur (Rajasthan)

iii.                Plastic industry in Bombay

iv.                Khetri Copper Project in Rajasthan

v.                  Textile industry at Bombay and Ahmedabad

vi.                Sugar industry in Maharashtra and U.P.

vii.              Glass and Bangle industry at Firozabad

viii.            Woollen carpets at Mirzapur

ix.                Silken sarees at Kanjiwaram ( Tamil Nadu )

x.                  YMCA Institute of Engineering at Faridabad

xi.                Indian Oil Refinery at Mathura

xii.              Iron foundaries at Agra

xiii.            Brass sheet industry at Moradabad

xiv.            Bed sheet industry at Sholapur.

xv.              Escort Tractors Ltd. At Faridabad.

 

  1. a. What do you understand by “Centralised Production Planning and Control”?   Give its advantages.

 

b. What is the position of P.P.C. in a works organization? Show it with the help of a chart.

 

  1. a. What do you understand by the ‘Follow up’ function of production planning and control? Explain

 

b. Give a specimen of “Gantt Chart” which is normally used in the production planning and control department and describe briefly how it could be used for checking the actual progress of a job against the schedule

 

 

  1. a. What are the various Indirect Expenses which are essential in estimating the total cost? Explain

 

b. What do you understand by depreciation? Explain

 

 

  1. a. What is the purpose of Work Measurement? Enumerate its uses

 

b. What are the various allowances considered in Time Study?

 

c. Define “Rating”. What is its necessity?

 

 

  1. a. What are the techniques of work measurement? Explain each of them briefly.

 

b. Why is a job broken down into elements and what are the general rules for selection of elements?

 

 

  1. a. How ‘management functions’ differ from ‘administrative functions’ specially in the context of ‘differentiation’ and ‘integration’ activities involved in realising the organizational objectives?

 

b. Distinguish between ‘formal’ and ‘informal’ type of communication system.

 

c. Considering a manufacturing organization as a ‘socio-technical’ system indicate how the four principal functions of management are interrelated.

 

  1. a. Explain the assumption underlying PERT and CPM network models applied in Project Management.

 

b. How is PERT different from CPM? Explain their fields of application

 

c. A project is composed of seven activities whose time estimates are listed in the following table. Activities are identified by their beginning(i) and ending(j) mode numbers:

 

Activity

Estimated duration in weeks

I

j

Optimistic

Most Likely

Pessimistic

1

2

1

1

7

1

3

1

4

7

1

4

2

2

8

2

5

1

1

1

3

5

2

5

14

4

6

2

5

0

5

6

3

6

15

 

i.                    Draw the project network and identify all paths for its completion.

ii.                  Find the expected duration and variance for the project

iii.                Calculate the early and let occurrence time for each mode. Calculate expected project length.

iv.                Calculate the stack for each activity

 

 

  1. What are the basic differences between

i.                    Operation process chart

ii.                  Flow process chart

iii.                Flow diagram, and

iv.                String Diagram.

 

Draw sample charts with a specific product in mind to explain the characteristics of these techniques of Work Study.